2 unit 6 room one story building
6 room 2 unit floor plan with 1620 square foot

*The provided unit rates are based on the information approximately .
Assumptions:
* Wall thickness: 5 inches
* Foundation: Strip foundation
* Roof: RCC flat roof
* Plaster: Single coat
* Paint: 3 coats
* Cement: 540 BDT per bag
* Steel: 97000 BDT per ton
* Sand: 35 BDT per cubic foot
* Tiles: 65 BDT per square foot
* Plumbing package: 50000 BDT
* Door price: 13000 BDT per piece
* Windows: 10000 BDT per piece
* Daily labor cost: 800 BDT
* Electrical total package: 100000 BDT
* Location: Bangladesh
* Mobilization cost: 100000 BDT
Calculations and Estimates
1. Foundation
* Total length of walls: 113 + 113 + 30 + 30 + 45 + 45 = 376 feet
* Foundation width: Assuming 1 foot
* Foundation volume: 376 * 1 * 1 = 376 cubic feet
* Cement: 376 cubic feet * 1.5 bags/cubic foot = 564 bags
* Cement cost: 564 bags * 540 BDT/bag = 304,440 BDT
* Steel: Assuming 50 kg/cubic foot
* Steel weight: 376 cubic feet * 50 kg/cubic foot = 18,800 kg
* Steel cost: 18,800 kg * 97000 BDT/ton = 1,822,600 BDT
* Sand: 376 cubic feet
* Sand cost: 376 cubic feet * 35 BDT/cubic foot = 13,160 BDT
* Labor: Assuming 10 days for foundation work
* Labor cost: 10 days * 800 BDT/day = 8000 BDT
* Total foundation cost: 304,440 BDT + 1,822,600 BDT + 13,160 BDT + 8000 BDT = 2,148,200 BDT
2. Superstructure
* Wall area: 1620 square feet * 2 (for both sides) = 3240 square feet
* Wall volume (assuming 5 inches thickness): 3240 square feet * 5/12 feet = 1350 cubic feet
* Cement: 1350 cubic feet * 1.5 bags/cubic foot = 2025 bags
* Cement cost: 2025 bags * 540 BDT/bag = 1,093,500 BDT
* Steel: Assuming 50 kg/cubic foot
* Steel weight: 1350 cubic feet * 50 kg/cubic foot = 67,500 kg
* Steel cost: 67,500 kg * 97000 BDT/ton = 6,557,500 BDT
* Sand: 1350 cubic feet
* Sand cost: 1350 cubic feet * 35 BDT/cubic foot = 47,250 BDT
* Bricks: Assuming 60 bricks/square foot
* Brick quantity: 3240 square feet * 60 bricks/square foot = 194,400 bricks
* Brick cost: (Assuming 100 bricks/bag) 194,400 bricks / 100 bricks/bag * 500 BDT/bag = 972,000 BDT
* Labor: Assuming 30 days for superstructure
* Labor cost: 30 days * 800 BDT/day = 24,000 BDT
* Total superstructure cost: 1,093,500 BDT + 6,557,500 BDT + 47,250 BDT + 972,000 BDT + 24,000 BDT = 8,794,250 BDT
3. Finishing
* Plaster: 3240 square feet
* Plaster cost: 3240 square feet * 20 BDT/square foot = 64,800 BDT
* Paint: 3240 square feet * 3 coats * 15 BDT/square foot/coat = 145,800 BDT
* Tiles: 1620 square feet
* Tile cost: 1620 square feet * 65 BDT/square foot = 105,300 BDT
* Plumbing package: 50,000 BDT
* Electrical package: 100,000 BDT
* Doors (assuming 8 doors): 8 doors * 13000 BDT/door = 104,000 BDT
* Windows (assuming 12 windows): 12 windows * 10000 BDT/window = 120,000 BDT
* Labor: Assuming 20 days for finishing
* Labor cost: 20 days * 800 BDT/day = 16,000 BDT
* Total finishing cost: 64,800 BDT + 145,800 BDT + 105,300 BDT + 50,000 BDT + 100,000 BDT + 104,000 BDT + 120,000 BDT + 16,000 BDT = 706,100 BDT
4. Mobilization Cost
* Mobilization cost: 100,000 BDT
Disclaimer:
* This estimate is a rough approximation and may vary based on specific factors like material quality, labor rates, and unforeseen circumstances.
* It's highly recommended to consult with local contractors or architects for a more accurate and customized quote.
Please note: This is a rough estimate. Actual costs may vary based on specific factors and local market conditions. For a more accurate quote, it's recommended to consult with local contractors and architects.